Instrument Air
Design, engineering and construction supervision to install new instrument/service compressed air system. Capital Costs: $1,000,000 The post Instrument Air appeared first on APEX Engineering.
View ArticleFuel Blending Control System
Engineering and design for the installation of a PLC-controlled fuel blending control system including programming and screen configuration. Capital Costs: $375,000 The post Fuel Blending Control...
View ArticleCoal Dust Suppression System
Design, engineering and start-up of coal dust suppression system. Capital Costs: $350,000 The post Coal Dust Suppression System appeared first on APEX Engineering.
View ArticleFuel Handling Conveyor
Design and engineering of a fuel handling conveyor. Capital Costs:$300,000 The post Fuel Handling Conveyor appeared first on APEX Engineering.
View ArticleDust Control and Collection
Design and construction management to improve emissions by collection of fugitive dust. Capital Costs: $250,000 The post Dust Control and Collection appeared first on APEX Engineering.
View ArticleBoiler Injection
Provided a basic engineering package design to store and inject into the boilers a powder activate carbon (PAC) for Hg removal. Capital Costs: $1,200,000 The post Boiler Injection appeared first on...
View ArticleGenerator Installation Design
Design for installation of 500kw diesel generator to provide power to critical plan loads (fire protection pumps, turbine lube oil, and packaging turning gear pumps) during a site power loss. Capital...
View ArticleDust Collection Design
Project entailed the design of a dust collection system to collect dust emitted during bag change-outs for the baghouse on a fly ash silo. Capital Costs: $250,000 The post Dust Collection Design...
View ArticleCarbon Storage Design
Project entailed the design of an activated carbon storage and pneumatic transfer system from 2-30 day storage silos to 3-3 day unit pair tanks for Hg emission reduction. Detailed design included...